Saturday, November 28, 2009

How Much To Tip For Waxing

THE FINISHED RESTORATION TO THE SHRINE OF ADONAI BRUCOLI















































Note to readers The post is accompanied by some photos in the text
the bottom of the page you will find the corresponding links
Images can be enlarged


the ravages of time and of the quake damage from the so-called restoration .

Often the man makes the illusion that these works will last infinitely in time.
Certain works, it is true they are defying the centuries and millennia (pyramids, temples, churches, convents). But time and nature, in the end, if the man did not defend them if the resume. The blanket of sand or vegetation sometimes does not pass even a generation. He also experienced the Sanctuary of the Madonna Adonai: the ancient underground, where Christians of the third century had painted on the rock one of the oldest images of the Mother of God (photo 1), has remained hidden for twelve centuries before being rediscovered by chance a boy, to live, looked after the cattle. How many things of the past we
found after thousands of years by archaeologists and scholars, and maybe still admiring.
But how did they do? And these were not the super-technological means today.
The Roman aqueducts, made stone by stone, the columns of Greek temples that abound in Sicily, resist most of today's bridges made of steel and reinforced concrete, the concrete of the Colosseum is still there, intact and mysterious, ancient theaters and amphitheatres can be used even after thousands of years, other similar works, but recent, need constant maintenance and very long time for restoration.
Today, after some renovation, but the facts and not wasting money and under the supervision of the Superintendence high technology for civil protection, only a few months later they say: "but here everything is falling to pieces" (photo 2).
Often, builders will go away cursing the fact that just finished work, you must start again. The blame is almost always material, the rush to finish, falling short of manpower, the money that has been insufficient.
Nature has its cycles for the birth and death, build and destroy, one day, week, month, year. I often came spontaneously exclaimed after seeing the results of certain works, "only God is eternal." At least we console with this answer that no one can contradict. The Sanctuary
dell'Adonai, the origin of which we know little in a few days there will be "returned".
The annexed monastery built on several occasions between XVI and XIX century, has "suffered" the restoration work following the earthquake of 1990.
It was so "refurbished" it is definitely gone all traces of its age.
is true that to put it "safely" have altered the appearance inside and outside, but it is true that with some technical device (photo 3a 3b 3c), without hiding behind the excuse that "the approved project can not be changed "If they could maintain appearance.
has disappeared also the "sobriety" of the premises of the monastery, a characteristic that remained almost unchanged over time. The poverty of the friars did not allow special decorations or as elaborate decorations in other convents of his time. But every single stone (photo 4a 4b) exuded spirituality, and the manual labor of those brothers who first had to isolate themselves within the walls in most cases used only precious swords and cutlery. All context
called only for recollection (photo 5) and prayer.
Some of these stones are inexplicably disappeared, suggestive corners (Photo 6) of the centuries-old monastery were arbitrarily transformed with dubious aesthetic tastes, other parts have been demolished (photo 7) and was not fixed by deleting the historical memory of the ancient site. Probably as soon as possible to restore the degradation time, in another beautiful place you have forgotten to redo the roof (photo 8) that, even before the works of conservation and restoration, already existed. Perhaps, when drawing up the restoration project, it was thought more to the walls and floors not to "return to life" (Photo 9) to a place that has always distinguished itself for having restored my faith in life for many who almost five hundred years have lived, leaving behind an empty life, and sometimes lived in the violence of war.
The Sanctuary of the Madonna Adonai was one of those structures "sacred" that not even the violence of nature and of man has managed to clear: even the catastrophic earthquake of 11 January 1693 did not dare to touch: in the midst of that terrible devastation that had ruined hundreds of churches and convents in Sicily half "was the only church in the territory of Augusta not to suffer any harm." Sanctuary Adonai
Paradoxically, after five centuries of history and life, from the same Italian Civil Protection, which would have the institutional responsibility to prevent and mitigate the seismic risk, and currently in other parts of Italy (Abruzzo) is working to not to lose the memory of the past, here has been able to do the opposite, with the gate.
were gone even the couplets on the lintels (Photo 10b 10c 10th) port of the ancient monks' cells ... ....
usually done to restore it rejoices and celebrates but not in this case because, after the restoration will need another renovation, before it finally lost all traces of a piece of our history.









Brucoli November 28, 2009










Sac. Prisutto Palmiro









Shrine Rector



Images supplied:

(photo 1) Mother of God
http://www.flickr.com/photos/prisutto/3196668324/

(photo 2) all fell to pieces
http:/ / www.flickr.com/photos/prisutto/3449959152/

(photo 3a 3b 3c) This technical
http://www.flickr.com/photos/prisutto/3209233069/
http://www .flickr.com/photos/prisutto/3503627727 /
http://www.flickr.com/photos/prisutto/3504442606/in/photostream/

(4th photo 4b) single stone
http:// www.flickr.com/photos/prisutto/3449934738/
http://www.flickr.com/photos/prisutto/3449931256/

(photo 5) suggestive corners cloistered
http://www.flickr.com/photos/prisutto/3449922380/

(photo 6) evocative corners terrace
http://www.flickr.com/photos/prisutto/3449932914/

(photo 7) shares have been demolished
http://www.flickr.com/photos/ prisutto/3209292223 /

(photo 8) to redo the roof http://www.flickr.com/photos/prisutto/3932384568/in/set-72157622405489062/

(Photo 9) to resume life millstone
http://www.flickr.com/photos/prisutto/3196669842/

(photo 10b 10c 10th) couplets on the lintels
http://www.flickr.com/photos/prisutto/3503868488/
http://www.flickr.com/photos/prisutto/3503056401/in / photostream /
http://www.flickr.com/photos/prisutto/3503046515/


(photos 11a and 11b) sanctuary facade
http://www.flickr.com/photos/prisutto/3401434494 /
http://www.flickr.com/photos/prisutto/3494531170/in/set-72157617507242797/

(foto12) http://www.flickr.com/photos/prisutto/3494525308/in / set-72157617507242797 /

Thursday, November 26, 2009

Blueprints For Offices



DATE MATCH RESULT
15 September 2009 Juventus - Bordeaux 1-1 Maccabi Haifa
September 15, 2009 - Bayern Monaco 0-3 September 30, 2009
Bayern Monaco - Juventus 0-0
Bordeaux September 30, 2009 - Maccabi Haifa 1-0
21 October 2009 Bordeaux - Bayern Monaco 2-1 Juventus
October 21, 2009 - Maccabi Haifa 1-0
November 3, 2009 Bayern Monaco - Bordeaux 0-2 Maccabi Haifa
November 3, 2009 - Juventus 0-1
November 25, 2009 Bordeaux - Juventus 2-0 Bayern Monaco
November 25, 2009 - Maccabi Haifa 1-0 Maccabi Haifa
December 8, 2009 - Bordeaux - December 8, 2009
Juventus - Bayern Monaco - Group A Champions
Calendar League 2009/2010 DATE MATCH RESULT
September 15, 2009 Wolfsburg - CSKA Moscow 3-1 Besiktas
September 15, 2009 - Manchester United 0-1
September 30, 2009 CSKA Moscow - Besiktas 2-1
September 30, 2009 Manchester United - Wolfsburg 2 -
October 21, 2009 Wolfsburg 1 - Besiktas 0-0
21 October 2009 CSKA Moscow - Manchester United 0-1 Besiktas
November 3, 2009 - Wolfsburg 0-3
November 3, 2009 Manchester United - CSKA Moscow 3-3
November 25, 2009 Manchester United - Besiktas 0-1 CSKA Moscow
November 25, 2009 - Wolfsburg 2-1 Wolfsburg
December 8, 2009 - Manchester United - December 8, 2009
Besiktas - CSKA Moscow -
Calendar Group B Champions League 2009/2010 DATE MATCH RESULT
September 15, 2009 Zurich - Real Madrid 2 -5
September 15, 2009 Marseille - Milan 1 - 2
September 30, 2009 Real Madrid - Marseille 3-0
September 30, 2009 Milan - Zürich 0-1
October 21, 2009 Real Madrid - Milan 2-3
October 21, 2009 Zurich - Marseille 0-1 AC Milan
November 3, 2009 - Real Madrid 1-1 Marseille
November 3, 2009 - Zurich 6-1
November 25 2009 Milan - Marseille 1-1 Real Madrid
November 25, 2009 - Zurich 1-0
December 8, 2009 Zurich - Milan - December 8, 2009
Marseille - Real Madrid -
Calendar Group C Champions League 2009/2010 DATE MATCH RESULT
September 15 2009 Chelsea - Porto 1-0 Atletico Madrid
September 15, 2009 - APOEL Nicosia 0-0
Porto September 30, 2009 - Atletico Madrid 2-0 APOEL Nicosia
September 30, 2009 - Chelsea 0-1 Porto
October 21, 2009 - APOEL Nicosia 2 - 1
21 October 2009 Chelsea - Atletico Madrid 4-0 APOEL
November 3, 2009 Nicosia - Porto 0-1
November 3, 2009 Atletico Madrid - Chelsea 2-2
November 25, 2009 Porto - Chelsea 0-1 APOEL Nicosia
November 25, 2009 - Atletico Madrid 1-1
December 8, 2009 Chelsea - APOEL Nicosia -
08 Atletico Madrid December 2009 - Porto -
Calendar Group D Champions League 2009/2010 DATE MATCH RESULT
September 16, 2009 Liverpool - Debrecen 1-0
16 September 2009 Lyon - Fiorentina 1-0 Fiorentina
September 29, 2009 - Liverpool 2-0
September 29, 2009 Debrecen - Lyon 0-4
October 20, 2009 Debrecen - Fiorentina 3-4
20 October 2009 Liverpool - Lyon 1-2 Fiorentina
November 4, 2009 - Debrecen 5-2
November 4, 2009 Lyon - Liverpool 1-1
November 24, 2009 Debrecen - Liverpool 0-1 Fiorentina
November 24, 2009 - Lyon 1-0
December 9, 2009 Liverpool - Fiorentina - Lyon
December 9, 2009 - Debrecen -
Calendar Group E Champions League 2009/2010 DATE MATCH RESULT
September 16, 2009 Inter Milan - Barcelona 0-0 Dinamo Kiev
September 16, 2009 - Rubin Kazan 3-1 Rubin Kazan
September 29, 2009 - Inter 1 - 1
September 29, 2009 Barcelona - Dynamo Kiev 2-0
20 October 2009 Inter - Dinamo Kiev 2-2
Barcelona October 20, 2009 - Rubin Kazan 1-2 Dinamo Kiev
November 4, 2009 - Inter 1-2
Rubin November 4, 2009 Kazan - Barcelona 0-0 Barcelona
November 24, 2009 - Inter 2-0
November 24, 2009 Rubin Kazan - Dynamo Kiev 0-0 Inter
December 9, 2009 - Rubin Kazan - Dynamo Kiev
December 9, 2009 - Barcelona - Group F
Calendar Champions League 2009/2010 DATE MATCH RESULT
September 16, 2009 Stuttgart - Glasgow Rangers 1 - 1
September 16, 2009 Seville - Unirea Urziceni 2-0 Unirea Urziceni
September 29, 2009 - Stuttgart 1-1 Glasgow Rangers
September 29, 2009 - Sevilla 1-4
October 20, 2009 Glasgow Rangers - Unirea Urziceni 1-4
October 20, 2009 Stuttgart - Sevilla 1-3 Unirea Urziceni
November 4, 2009 - Glasgow Rangers 1-1
November 4, 2009 Sevilla - Stuttgart 1-1
November 24, 2009 Glasgow Rangers - Stuttgart 0-2 Unirea Urziceni
November 24, 2009 - Sevilla 1-0
December 9, 2009 Stuttgart - Unirea Urziceni -
December 9, 2009 Seville - Glasgow Rangers -
Calendar Group G Champions League 2009/2010 DATE MATCH RESULT
Olympiacos September 16, 2009 - AZ Alkmaar 1-0 Standard Liege
September 16, 2009 - Arsenal 2-3 Arsenal
September 29, 2009 - Olympiacos 2-0
29 September 2009 Az Alkmaar - Standard Liege 1-1 Az Alkmaar
October 20, 2009 - Arsenal 1-1 Olympiacos
October 20, 2009 - Standard Liege 2-1
November 4, 2009 Arsenal - AZ Alkmaar 4-1 Standard Liege
November 4, 2009 - Olympiacos 2-0
24 November 2009 AZ Alkmaar - Olympiacos 0-0
November 24 Arsenal 2009 - Standard Liege 2-0 Olympiacos
December 9, 2009 - Arsenal -
December 9, 2009 Standard Liege - Az Alkmaar -
Calendar Group H Champions League 2009/2010 DATE MATCH RESULT
February 16, 2010 - -
February 16, 2010 - -
February 17, 2010 - -
February 17, 2010 - -
February 23, 2010 - -
February 23, 2010 - -
February 24, 2010 - -
February 24, 2010 - -
knockout round Champions League 2009/2010 - ROUND MATCH RESULT DATE
March 9, 2010 - -
March 9, 2010 - -
March 10, 2010 - -
March 10, 2010 - -
March 16, 2010 - -
March 16, 2010 - -
March 17, 2010 - -
March 17, 2010 - -
knockout round Champions League 2009/2010 - RETURN DATE MATCH RESULT
March 30, 2010 - -
March 30, 2010 - -
March 31, 2010 - -
March 31, 2010 - -
Quarter Final Champions League 2009/2010 - ROUND MATCH RESULT DATE
April 6, 2010 - -
April 6, 2010 - -
April 7, 2010 - -
April 7, 2010 - -
Quarter Final Champions League 2009/2010 - RETURN DATE MATCH RESULT
April 20, 2010 - -
April 21, 2010 - -
Semi Final of Champions League 2009/2010 - ROUND MATCH RESULT DATE
27 April 2010 - -
April 28, 2010 - -
Semi Final of Champions League 2009/2010 - RETURN DATE MATCH RESULT
May 22, 2010 - - Final Champions League 2009/2010

Saturday, November 7, 2009

What Is A Good Muscle Car Daily Driver

RESPONSES AND LATE RECONSTRUCTION OF SERIES AUTOGIUSTIFICANTI


















ITALIAN REPUBLIC

Sicily Region Presidency



Department of Civil Protection Service in the province of Siracusa

Prot n 6981 of 05/11/2009


sent by fax to Syracuse
Prefecture Territorial Office of Government
Piazza Archimede, Syracuse

Via e-mail and PC to the Head of the Department of Civil Protection
Via Ulpian, 11 - Rome

Via e-mail the Director General of the Department of Civil Defense Regional

Via Abela, 5-Palermo

faxed to the superintendent to BB. CC and AA.
96100 Syracuse - Syracuse

sent by fax to the Archbishop of Syracuse
Piazza Duomo - Siracusa

Via e-mail the Rector of the Shrine of Mary SS.ma Brucoli
Brucoli (Augusta)



SUBJECT: Law 433 / 91. Brucoli Adonai Church and Convent. Reference notes of 15 226 06/08, and 26/10 of 15 September 2009.

am having the notes of this Office Prefecture - UTG - and about you after what has already been communicated to the streets to Dr. Shroud us October 12, specifying and clarifying what follows. With
contract 22/12/2006, Rep. No. 264, the Regional Department of Civil Defense, gave the GSG Enterprises Ltd. based in Agrigento, c / ESA-by Moses Chimento - sn, work on the recovery and conservation of Brucoli Adonai Church and convent for the total amount of net € .823.742,29.
These works were delivered under the provisions of the law, dated 19/12/2006 and the same should be completed in 365 days and, therefore, on 19/12/2007.
The work was completed On May 2, 2008 because during the process it was necessary to prepare two reports of variation in order to meet the needs arising in work in progress and to achieve the full functionality of the property, having regard primarily to the work done outside of ' area attributable to the convent.
All technical procedures - administrative set-up (original approval and subsequent variants) has been brought to the Curia through the head of the engineering of the same who participated in various conferences of service.
Following completion of the works will begin the procedures for the preparation of technical and administrative acts, preparatory to testing for the return of the property owner Ente.
note dated 20/06/2008, to acts of this service on 25/06/2008, the Archbishop of Siracusa, in fact, was required to have returned the property in the interim which initiated the process engineer - Administrative provided for.
The above process included, among other things, the performance of all the technical tests required by the applicable standards of safety and environmental protection (electrical, plumbing, heating, sewage discharge etc..) That were completed during the month November 2008.
At the same time, already with a note of July 23, 2008, the Rector of the Shrine contest run of some workers, mainly in the context of protecting the building, an attitude that in fact the first slowed and then stopped the cited provisional acceptance as discussed below.
In order to ascertain the correctness of the comments highlighted by the Rector of the Shrine, in fact, a note of 01/Agosto 2008, prot. N. 5919, the writer requested the DL and possibly the necessary clarifications about the requirements to be implemented.
The DL on the same day confirmed via fax that the works were carried out in accordance with the approved project and to variants and that the observations of the Sac. Prisutto were not relevant.
Both the DL that the contractor, respectively, with a note of the '1 August 2008 and August 4, 2008 were received, their negative opinion about the provisional acceptance to the Archbishop of Syracuse.
On 25/09/2008, moreover, was made a joint inspection, required by the Superintendence of Cultural Heritage and AA. Syracuse, in order to verify the correctness of the comments by the Rector of the Sanctuary with the note mentioned above, which involves, in addition to writing, even the DL, the representative of the Curia in the person of Eng. Felt, and the sac. Prisutto Palmiro. Following the inspection the said body, from the standpoint of protecting and preserving the property, had nothing to complain in order to carry out the work contracted and performed.
completed all the technical tests, in the building of the facilities created and acquired all the documents preparatory to the provisional, including clearance by the contractor on 07/10/2008, pending completion of the test, the writer in December 2008 authorizing the DL for the provisional delivery date which was fixed by the same DL, for the day 03/06/2009.
the fixed date, at the Shrine of Brucoli, in the presence of the writer, the DL, Enterprise, representative of the Curia, in the person of 'Mr. Felt, and the Rector of the Sanctuary, Sac. Palmiro Prisutto, was effect the necessary reconnaissance of the property, in order to prepare the required audit report. Once the survey were found working in some of the drawbacks, however modest, that does not invalidate the use of the property. Invited the company to their complete elimination. At this point the Sac. Prisutto refused delivery for which there remained nothing but wait for the testing work. Subsequently, the Rector of the Shrine
required another visit to the Superintendence of Cultural Heritage and AA. Syracuse, which was made on 19.5.2009, following which the Board reiterated, with the written opinion that the findings made by the Sac. Prisutto not concern the scope of their skills. Objected, however, on the demolition of an ancient portal, about which I'm currently testing (the writer has requested clarification from the DL), which, however, is out of the contract and shall not affect the use of the property and Ente his return as the owner, however, confirmed by the inspector in his report of 08 October 2009.
To date, operations testing, both static and technical - administrative, can be considered completed and the testing required before issuing the notice of acceptance, which were restored to the Fair Labor report of 08/10/2009.
Heard the test, for short routes, completion of the restoration work, ordered the contractors on 16/10/2009, the estimated date for delivery of the property can be set for mid November next

THE HEAD OF THE DEPARTMENT
F.to (Engineer Paul Burgo)
below is the same letter but with the additions of the sac. Prisutto Palmiro rector of the Shrine. The original parts are written in black, those of the rector in bold red .

ITALIAN REPUBLIC
Sicily Region Presidency


Department of Civil Protection Service in the province of Siracusa


Prot No. 6981 of 05/11/2009


sent by fax to Syracuse
Prefecture Territorial Office of Government
-Syracuse Piazza Archimede

Via e-mail and PC to the Head of the Department of Civil Protection
Via Ulpian, 11 - Rome
( marco.rinaldelli @ protezionecivile.it )

Via e-mail the Director General of the Department of Civil Defense Regional

Via Abela, 5-Palermo
(s.cocina @ protezionecivilesicilia.it)

Submitted by fax to the Superintendent of BB. CC and AA.
96100 Syracuse - Syracuse

sent by fax to the Archbishop of Syracuse
Piazza Duomo - Siracusa

Via e-mail the Rector of the Shrine of Mary SS.ma Brucoli
Brucoli (Augusta)
(palpri2@hotmail.it)


SUBJECT: Law 433/91. Brucoli Adonai Church and Convent. Reference notes of 15 226 06/08, and 26/10 of 15 September 2009.

am having this Office notes Prefecture - UTG - and about you after what has already been communicated to the streets to Dr. Shroud us October 12, specifying and clarifying what follows. With
contract 22/12/2006, Rep. No. 264, the Regional Department of Civil Defense, gave the GSG Enterprises Ltd. based in Agrigento, c / ESA-by Moses Chimento - sn, the work of recovery and Preservation of the Church and Convent of Brucoli Adonai for a total income of € .823.742,29.
These works were delivered under the provisions of the law, dated 19/12/2006 and the same should be completed in 365 days and, therefore, on 19/12/2007.
The work was completed on May 2, 2008 because during the process it was necessary to prepare two reports of variation in order to meet the needs arising in work in progress and to achieve the full functionality of the property, having regard mainly attributable to the work done outside of the convent.
All technical procedures - administrative set-up (original approval and subsequent variants) has been brought to the Curia through the head of the engineering of the same who participated in various conferences of service. ?????????????????
Following completion of the works will begin the procedures for the preparation of technical and administrative acts, preparatory to testing for the Ente return of the property owner.
note dated 20/06/2008, to acts of this service on 25/06/2008, the Archbishop of Siracusa, in fact, was required to have returned the property in the interim which initiated the process engineer - Administrative expected to respect.
The above process included, among other things, the performance of all the technical tests required by the applicable standards of safety and environmental protection (electrical, plumbing, heating, sewage discharge etc..) That were completed during the month November 2008. order to perform these tests, in the vain expectation of return, we were requested to enter the sanctuary by the three-phase electricity supply contract, which has been conducted in the second half of August 2008 only after the company has GSG arrears and paying your bills in the meantime we have agreed to speed with the company another contract but this did not appear making vacuum spend € 456. Since July 2008, even after an attempted burglary, yours truly declaring the complete lack of housing Shrine from the enterprise, will arrange a contract with a firm was active surveillance room to March 2009.
At the same time, already with a note of July 23, 2008, the Rector of the Shrine considered that the works carried out as soon as they were already visibly deteriorated challenged the execution of some jobs, mainly in the context of protecting ' building, an attitude that in fact the first slowed and then stopped the cited provisional acceptance as will below.
In order to ascertain the correctness of the comments highlighted by the Rector of the Shrine, in fact, a note of 01/Agosto 2008, prot. N. 5919, the writer requested the DL and possibly the necessary clarifications about the requirements to be implemented.
The DL on the same day confirmed via fax that the works were carried out in accordance with the approved project and to variants and that the observations of the Sac. Prisutto were not relevant. Nor was the fact the connection to the network Enel.
Both the DL that the contractor, respectively, with a note of the '1 in August 2008 and August 4, 2008 were received, their negative opinion about the provisional acceptance to the Curia Archbishop in Syracuse. So why should I sign the contract with Enel as I could not take advantage of the sanctuary? Meanwhile, the bills arrive and are paid from the shrine.
On 25/09/2008, moreover, was made a joint site inspection, required by the Superintendence of Cultural Heritage and AA. Syracuse, in order to verify the correctness of the comments by the Rector of the Sanctuary with the note mentioned above, which involves, in addition to writing, even the DL, the representative of the Curia in the person of Eng. Felt, and the sac. Prisutto Palmiro. Following the inspection the said body, from the standpoint of protecting and preserving the property, had nothing to complain in order to carry out the work contracted and performed. has "no objection" who did not know the condition of the premises before the "restoration" and this applies to all who were involved in various capacities in the restoration. From my point of view have been made disruptions to the status of places as the representative of the superintendent thought of the "concert" events and "cultural" that could be carried out on the upper courtyard of the shrine. On that occasion I have challenged to work towards the total disappearance of a barn which had previously presented photographic documentation. (I was told that photographs were "old" although there were photographs of the site means). Also on the same occasion contestai the fact that the result of demolition debris in landfills instead of being carried were scattered in the grounds of the sanctuary and those surrounding the shrine .
completed all the technical tests, in the building of the facilities created and acquired all the documents preparatory to the provisional, including clearance by the contractor on 07/10/2008, pending completion of the test, the writer in December 2008 (which had been operated without the administrative technical inspection one month after the maximum time of delivery) authorizing the DL for the provisional delivery date which was fixed by the same DL, for the day 06/03/2009. Date which have not been informed if not for people outside and in the same morning.
the fixed date, at the Shrine of Brucoli, in the presence of the writer, the DL, Enterprise, representative of the Curia, in the person of 'Mr. Felt, (Mr. Felt at that time did not represent plus the Curia was only present as an observer to the unofficial and has pointed out) and the Rector of the Shrine, the Sac. Palmiro Prisutto, was in fact the necessary reconnaissance of the property, in order to prepare the required audit report. Once the survey were found working in some of the drawbacks, (on which he spoke of waiting to return four more times) however modest, that does not invalidate the use of the property. Invited the company to their complete elimination. At this point the Sac. Prisutto refused delivery for which there remained nothing but wait for the testing work. that has already been done, see note to the Department of Civil Protection PROT. N. DPC/SISM/28550 ROME, 20/04/2009 http://santuarioadonaibrucoli.blogspot.com/2009/09/non-tutti-hanno-fatto-il-loro-dovere.html .
(The Prisutto as the engineer. Burgo had proposed an out-out - or so or after the test - called for an additional week to inform the Curia). On that occasion, the owner of giving orders to seal the entire area of \u200b\u200bthe sanctuary, including the garden and the area green in fact also prevent the maintenance up to date . Subsequently, the Rector of the Shrine
required another visit to the Superintendence of Cultural Heritage and AA. Syracuse, which was made on 19.5.2009, following which the Board reiterated, with the written opinion that the findings made by the Sac. Prisutto not concern the scope of its powers. Objected, however, on the demolition of an ancient portal, and other already reported in the note of July 23, 2008) with respect to which they are in the course of testing (the writer has requested clarification from the DL), which, in any case, it appears from outside 'contract and not impede the use of the property and its return as Ente owner, however, confirmed by the inspector in his report of 08 October 2009.
To date, operations testing, both static and technical - administrative, can be considered completed and the testing required before issuing the notice of acceptance, which were restored to right relationship of working of 08/10/2009. (various works, some of which began on the fifth intervention)
Heard the test, for short routes, completed the restoration work, ordered the contractors on 16/10/2009, the expected date for return the property (rightly I use the term "property" because of the ancient monument was almost completely destroyed) can be set for mid November next


THE HEAD OF THE DEPARTMENT
F.to ( Mr. Paul Burgo)
Sac. Prisutto Palmiro
Shrine Rector